Owner : | Land Transport Authority |
General contractor : | Lum Chang Buildings Contractors Pte Ltd |
Application : | Soft-Eye |
FiReP Solution : | GRP mesh, GRP bolts |
Construction date : | 1. 03/2010 2. 07/2010 |
TBM information : | |
Products : |
1. FiReP Rebar straight d=40mm FiReP Rebar Double Loop d=32mm 2. FiReP Rebar straight d=40mm, d=32mm, d=22mm FiReP Rebar stirrup d=32mm, d=22mm, d=16mm |
General information : | 1. Petir Station: 2 TBM break-through FRP reinforced bore pile 2. Zone 6 2 TBM break-through FRP reinforced bore piles |